The office of the Director Works is responsible for the quality infrastructure development of the FATA University. It is strategizing the construction work as per the approved Master Plan and is adopting proper monitoring and evaluation of the civil work in regard to the construction of various buildings of the FATA University. It is also managing all sorts of physical works in the existing building.
ESTABLISHMENT OF THE FATA UNIVERSITY (Phase-1)
STATUS OF ONGOING WORKS PACKAGES
(Up to March, 2021)
S.No |
Name of Work |
Cost Rs (M) |
Date of Commencement |
Date of Completion |
Updated Physical Progress |
1 |
(Package-1) Construction of Boundary wall, Main Gate, Reception Room & Security Watch Towers. |
36.37 |
17-11-2017 |
Completed |
100% |
2 |
(Package-2) Construction of 4.No.s of Tube Wells , Overhead Water Tank 50,000 Gallon Capacity& Underground water Reservoir 30,000 Gallon Capacity |
33.00 |
09-04-2018 |
Completed |
100% |
3 |
(Package-3) Construction of Two Academic Blocks |
279.037 |
18-07-2018 |
18-07-2021 |
64% |
4 |
(Package-4) Construction of Student & Bachelor Hostels |
284.614 |
03-09-2018 |
03-09-2021 |
71% |
5 |
(Package-5) Construction of Admin Block, Central Library, Sports Gymnasium and Common Facilities Centre |
231.907 |
31-10-2018 |
31-12-201 |
50% |
6 |
(Package-6) Construction of Faculty & Staff Residencies |
58.191 |
03-06-2019 |
03-04-2021 |
58% |
7 |
(Package-7) Construction of External Developments |
147.149 |
22-02-2019 |
22-02-2021 |
55% |